Accelerator Report: Overcoming setbacks, antiprotons return as LHC recovers luminescent brilliance

The AD operations team received on Friday, 1 June – 12 days earlier than rescheduled – the green light from the AD injection kicker expert: beam could be injected again in the AD ring

News
Accelerators
06 June, 2023

Accelerator Report: Full house in the LHC

On 11 May, four days before the original schedule had set a target of 1200 bunches per beam, the LHC made its final intensity ramp-up step to 2400 bunches per beam

News
Accelerators
24 May, 2023
Accelerators
News
24 May, 2023

Accelerator Report: mostly on schedule, sometimes not…

The beam commissioning of the Antiproton Decelerator will start on 12 June, and the aim is to deliver antiprotons to the eagerly waiting AD-ELENA experiments on 30 June

News
Accelerators
10 May, 2023

Accelerator Report: Crescendo at the LHC following the first stable beams at 6.8 TeV

Another important milestone was achieved in the LHC beam commissioning: on 21 April, the LHC Engineer in Charge declared “stable beams” at 6.8 TeV, the first time in 2023

News
Accelerators
27 April, 2023

HiLumi News: Recovery of an HL-LHC niobium–tin magnet

The successful replacement of a coil in an HL-LHC niobium–tin quadrupole magnet by the US Accelerator Upgrade Project team has showcased this crucial technology’s flexibility and cost-effectiveness

News
Accelerators
26 April, 2023

Accelerator Report: Beam is back in the LHC

News
Accelerators
06 April, 2023
Accelerators
News
06 April, 2023

Kicking off

Following the installation of kicker magnets that are more heat resistant and their successful tests during the SPS scrubbing run, the SPS is getting ready for High-Luminosity LHC operation.

News
Accelerators
04 April, 2023
Accelerators
News
04 April, 2023

A spring awakening: CERN’s accelerators gear up for 2023

Following the winter shutdown, the injectors and accelerators are preparing for the 2023 data-taking season

News
Accelerators
29 March, 2023

Accelerator Report: Preparing for the upcoming LHC restart

With the progressive recommissioning of the injectors – including, now, the SPS – the various types of beam are being set up and are gradually reaching the downstream accelerators

News
Accelerators
22 March, 2023

HiLumi News: New CERN niobium–tin magnet energises the HL-LHC programme

A second 7.2-metre-long HL-LHC triplet quadrupole has reached the currents needed for 7 TeV operation, with higher performances

News
Accelerators
21 March, 2023